Case Study
de l’Épée
Parking spaces are now EV Ready thanks to the RVE technologies installed in this 6-unit condo building in Montreal. The installation was carried out by the team at Lilco Électrique inc.
Technical Specifications
Type of construction
existing building (retrofit)
Type of occupancy
condo
Building size
25 units and moins
Number of floors
5 and less
Number of parking spaces
25 and less
Location of electricity meters
accessible from the parking spaces
Location of parking spaces
indoor, covered, and outdoor with possible wet conditions
Type of parking spaces
assigned
Products used
Challenge
Powering an electric vehicle charging infrastructure in a multi-unit building where the electric meters are located in the garage basement (accessible).
Solution
Using a homogenous solution was possible to power charging infrastructure between the units of this condo building and the EV chargers that were requested to be installed. Indeed, all meters are accessible, allowing the use of DCCs everywhere.
- DCC-9-BOX to provide charging infrastructure without installing chargers right away
- DCC-9 for units with an electrical panel of 125A and less in need of a charger now